Blog

Road upgrade underway between R72 and MR501 intersection in East London

TRAFFIC ADVISORY: Immediate
Road upgrade underway between R72 and MR501 intersection in East London

Eastern Cape, 7 November 2023: The upgrading of the intersection between R72 Section 4 and MR501, at Kidd’s Beach in East London, is ongoing.

The project entails the lowering of the MR501 to pass underneath the R72 intersection through a concrete bridge structure, complete with the construction of the new on- and off-ramps, with new improved road signage. The anticipated completion date is May 2024.
The project is now at the stage where the roads need to be diverted in order to process with the next phases of the works.
The diversion will be in place from mid November 2023 to May 2024, during which time two-way traffic will be maintained via the diversion.

Road users of the R 72 Section 4 and MR 501 intersection, Kidd’s Beach at KM 42.08 (road marking), are requested to proceed with extreme caution on these sections of the roads and to obey the road signs and demarcations.
The traffic on the MR501 in and out of Kidd’s Beach, from the R72, will be diverted onto the new temporary bypass road to allow for the works to proceed.

“The developer of the Kidd’s Beach Green Estate Development, together with the appointed engineers, Mariswe Consulting, said that significant progress has been made to the intersection works,” said Mbulelo Peterson, SANRAL Southern Regional Manager.

SANRAL TAKES PUBLIC CONSULTATIONS ON INTERIM PREFERENTIAL PROCUREMENT POLICY TO KWAZULU-NATAL

MEDIA RELEASE

SANRAL TAKES PUBLIC CONSULTATIONS ON INTERIM PREFERENTIAL PROCUREMENT POLICY TO KWAZULU-NATAL

Pietermaritzburg, 6 November 2023 The South African National Roads Agency SOC Limited (SANRAL) will on Wednesday, 8 November 2023, continue its series of stakeholder engagement session at various venues in and around KwaZulu-Natal as part of public consultations on an Interim Preferential Procurement Policy (PPP).

The main stakeholder engagement session in KwaZulu-Natal will take place at Pietermaritzburg City Hall and will also be linked virtually to venues in Durban, Kokstad and Jozini.

The decision to withdraw SANRAL’s new Preferential Procurement Policy, which came into effect in May 2023, was taken by the Board on 23 October 2023 after careful consideration of the legal challenges to the policy launched by construction companies in various courts across the country.

These legal challenges would have prevented SANRAL from processing some 80 tenders worth billions of Rands, with significant negative consequences for the fulfilment of the roads agency’s constitutional and statutory mandate.

The purpose of the stakeholder engagement meetings is to enable SANRAL to receive inputs and contributions from interested and affected stakeholders to present a roadmap for implementation of the interim PPP.

SANRAL urges all interested and affected stakeholders to participate in this consultative process to facilitate a speedy resolution to any potential obstacles that would delay the roads agency from meeting its mandate to build and maintain the country’s road infrastructure network and pursue its transformation objectives.

Satellite venues:

Durban: Olive Conference Centre

Kokstad: Kokstad Youth Centre

Jozini: Hlabisa Community Hall

For further information please contact: Zenzele Bam on 072 891 5290 or Siyabonga Khuzwayo on 083 260 3555 or sanral@fticonsulting.com

 

SANRAL to engage military veterans in the Eastern Cape on economic opportunities within its road infrastructure build programme

MEDIA ALERT

SANRAL to engage military veterans in the Eastern Cape on economic opportunities within its road infrastructure build programme 

Eastern Cape, 5 November 2023 – The South African National Roads Agency SOC Ltd (SANRAL) will host a stakeholder engagement session with military veterans in the Eastern Cape in the Buffalo City Metropolitan Municipality on 7 November 2023. 

SANRAL will engage the military veterans on its transformation agenda that ensures participation of previously marginalised groups, including women, youth, people with disabilities and military veterans – in all its road infrastructure development projects.

Furthermore, the stakeholder engagement session is intended to introduce SANRAL, its road infrastructure development mandate and its policies to Eastern Cape military veterans.

Organs of state who will also be engaging the military veterans include:

  • Construction Industry Development Board (CIDB);
  • Eastern Cape Provincial Treasury;

  • National Department of Mineral Resources and Energy;

  • Small Enterprise Development Agency (SEDA); and,

  • Eastern Cape Development Corporation (ECDC).

Members of the media are invited as follows: 

Date: Tuesday, 7 November 2023

Time: 10h00 – 13h00

Venue: Christian Centre, Abbotsford, East London

 

RSVP:

Buli Mgojo on 078 007 5787 or buli.mgojo@fticonsulting.com

Three Free State Provincial Roads Fall Under The Management Of Sanral

MEDIA RELEASE
THREE FREE STATE PROVINCIAL ROADS FALL UNDER THE MANAGEMENT OF SANRAL

Pietermaritzburg, 3 November 2023 – Three provincial roads in the Free State scheduled for repairs and maintenance are set to fall under the jurisdiction of the South African National Roads Agency SOC Limited (SANRAL).
According to the Government Gazette of 27 October 2023, the roads handed over to SANRAL are the R26, R74 and R34, which connect the Free State to neighbouring provinces.

“The upgrades to these road corridors will provide a massive boost to the economy of the region and will greatly increase the road capacity in the area”, said Dumisani Nkabinde, Regional Manager of SANRAL’s Eastern Region.
“These areas are the lifeblood of our agricultural economy and as SANRAL we have to ensure that continuous road upgrades and maintenance will enable farmers and the rural communities to transport their goods, services and produce to the markets on roads that are safe to use.

“Under SANRAL’s management, these roads will stimulate economic activity, provide greater access for local communities and enable all motorists to travel on safe and secure roads”.

The roads that will be connecting the provinces are the R26, Ladybrand to Bethlehem, a distance of about 163km; the R34, northwest Free State provincial border to the KwaZulu-Natal provincial border covering a distance of some 406km; and the R74, connecting Harrismith in the Free State to the Kwazulu-Natal border, a distance of about 31km.

“This is a significant step towards alleviating pressure from the provinces and making roads safer. With these additions, SANRAL is moving towards expanding its network from the current 23 500km to some 35 000km,” Nkabinde said.

“This will not only benefit road users but local communities in the form of job opportunities and small businesses through sub-contracting.”

SANRAL surpasses contract participation goals on mega Msikaba Bridge construction

Media Release
SANRAL surpasses contract participation goals on mega Msikaba Bridge construction

Lusikisiki, Eastern Cape, 4 November 2023: The South African National Roads Agency SOC Limited (SANRAL) has exceeded its targets for locals to benefit from the construction of the Msikaba Bridge. Msikaba is one of two-mega-bridges on the N2 Wild Coast Toll Road (N2WCR).

SANRAL reported today that it had already exceeded its contract participation goals (CPG) for the Msikaba Bridge, with more than R550 million spent on targeted enterprises (Small, Medium, Micro Enterprises and suppliers). This translates into huge economic impact for Eastern Cape and local communities, with massive socio-economic benefits flowing to the region.

The report featured in a meeting of the N2 Wild Coast Road (N2WCR) Political Oversight Committee (POC) meeting held at the Lusikisiki Resource Centre. The meeting was attended by the Chairperson of the committee, MEC for Transport and Community Safety, Mr Xolile Nqatha, MEC for Cooperative Governance and Traditional Affairs, Mr Zolile Williams, the Mayor of Ingquza Hill Local Municipality, Councillor Nonkosi Pepping, the Mayor of Port St Johns, Councillor Nomvuzo Mlombile-Cingo, and traditional leaders affected by the N2 Wild Coast Road development.

The Msikaba Bridge contract’s CPG for targeted enterprises (that is SMMEs and suppliers) is a minimum of thirty percent of the contract value (R1.65 billion). To date R553.2 million (107% of the target) has been spent on 157 targeted enterprises which comprises 44 suppliers, 52 service providers and 61 sub-contractors. R92.8 million has been spent on wages of local targeted labour, which is 108% of the 5% CPG target (R86 million). Meanwhile 453 full-time equivalent jobs have been created to date, with 391 of these being occupied by local persons.

“SANRAL has risen to the occasion once again and has made a huge difference to the lives of people in local communities through job creation and business opportunities on the N2 Wild Coast Road development. This region will never be the same. We appreciate SANRAL’s drive for socio-economic development, which also places an emphasis on a consultative approach and stakeholder engagement,” said MEC Nqatha.

The meeting provided a progress report on the N2 Wild Coast Road project and the socio-economic impact on communities as a result of the project. The meeting engaged the traditional leadership on issues of contention including introduction of projects to the affected traditional leadership (“ukukhahlela”) prior to commencement, issues around contested traditional leadership, access to villages, project disruptions and delays, as well as encroachment on SANRAL’s road reserve.

The traditional leadership raised concerns about the interdicted SANRAL contract for the construction of the road from Lingeni to the Msikaba Bridge, saying that the delay presented challenges in the community, particularly for the households affected by relocation who are now in limbo. They further urged SANRAL to engage stakeholders opposed to construction of the highway, such as pressure groups opposed to the current alignment in the Amadiba area The traditional leaders urged SANRAL to ensure prompt progression of the project.

MEC for Cooperative Governance and Traditional Affairs, Mr Zolile Williams, said he appreciated the cooperation from the traditional leadership on the N2WCR development. He cautioned that it was important to understand the process of “ukukhahlela” and the potential exploitation thereof. The MEC said that the Eastern Cape House of Traditional Leaders (ECHOTL) should be brought closer to the process to manage some of the contentious issues related to traditional leadership.

“Traditional leaders are part of the programme, they are fully behind the development. Their plea is for SANRAL to move with speed to construct the road and to ensure that no one will interfere with that. They have expressed interest to engage the Amadiba Crisis Committee which is opposing the project as they want to avoid anyone from preventing development in this area as this project will benefit local communities and address the road infrastructure backlog,” said MEC Williams.

About the N2 Wild Coast Toll Road project

The N2 Wild Coast Toll Road project entails a 410km stretch of road from East London to the Mtamvuna River on the border of Eastern Cape and KwaZulu-Natal provinces. While the project has been underway since 2011, construction on the major greenfield portion of the route between Port St Johns and Port Edward only started in 2016.
The project is endorsed by the Presidential Infrastructure Coordinating Commission (PICC) as a catalyst for economic development in the region. It is a major project for the province and forms part of government’s 18 Strategic Integrated Projects (SIPS). The N2WCTR is SIP3, South-Eastern node and Corridor Development, with the key purpose being to serve as a catalyst to uplift economic growth in the Eastern Cape and KwaZulu-Natal.

The project also consists of two mega-bridges, at Msikaba and Mtentu. There are also seven additional major river bridges and several interchange bridges that form part of the project.

The socio-economic impact of the N2WCTR Project offers a significant economic injection for local communities. The minimum 30% expenditure earmarked for targeted enterprise subcontractors and suppliers will result in over R4-billion flowing to SMMEs, the majority of which will be from the O.R. Tambo and Alfred Nzo district municipalities.

There is significant progress on the construction at the Msikaba Bridge on both the north and south banks. Construction of the Msikaba South pylon is currently at the 79% mark, at 80.5 meters (out of a total height of 126.7 meters), while the North bank is at the 70% mark, at 65.7 meters. Both the North and South bank pylons have exceeded the halfway mark. Jacking of the tower cranes on both banks is anticipated to be completed within November.

Construction of the Mtentu Bridge suffered years of delays following the project stoppage in 2018. The contract was subsequently retendered. On 1 November 2022, SANRAL awarded the contract for the construction of the Mtentu Bridge, valued at R4.05 billion, to the China Communications Construction Company (CCCC) and MECSA Construction joint venture (CCCC MECSA JV). The project is anticipated to be completed within a 54-month period, including a four-month ramp-up period. The commencement of the four-month ramp-up period started on 5 April 2023

THREE FREE STATE PROVINCIAL ROADS FALL UNDER THE MANAGEMENT OF SANRAL

MEDIA RELEASE

THREE FREE STATE PROVINCIAL ROADS FALL UNDER THE MANAGEMENT OF SANRAL

Pietermaritzburg, 3 November 2023 – Three provincial roads in the Free State scheduled for repairs and maintenance are set to fall under the jurisdiction of the South African National Roads Agency SOC Limited (SANRAL).

According to the Government Gazette of 27 October 2023, the roads handed over to SANRAL are the R26, R74 and R34, which connect the Free State to neighbouring provinces.

“The upgrades to these road corridors will provide a massive boost to the economy of the region and will greatly increase the road capacity in the area”, said Dumisani Nkabinde, Regional Manager of SANRAL’s Eastern Region.

“These areas are the lifeblood of our agricultural economy and as SANRAL we have to ensure that continuous road upgrades and maintenance will enable farmers and the rural communities to transport their goods, services and produce to the markets on roads that are safe to use.

“Under SANRAL’s management, these roads will stimulate economic activity, provide greater access for local communities and enable all motorists to travel on safe and secure roads”.

The roads that will be connecting the provinces are the R26, Ladybrand to Bethlehem, a distance of about 163km; the R34, northwest Free State provincial border to the KwaZulu-Natal provincial border covering a distance of some 406km; and the R74, connecting Harrismith in the Free State to the Kwazulu-Natal border, a distance of about 31km.

“This is a significant step towards alleviating pressure from the provinces and making roads safer. With these additions, SANRAL is moving towards expanding its network from the current 23 500km to some 35 000km,” Nkabinde said.

“This will not only benefit road users but local communities in the form of job opportunities and small businesses through sub-contracting.”

 

UPGRADE TO NATIONAL ROUTE 3, SECTION 2, FROM CATO RIDGE INTERCHANGE (KM 20.2) TO DARDANELLES (KM 26.6)

UPGRADE TO NATIONAL ROUTE 3, SECTION 2, FROM CATO RIDGE INTERCHANGE (KM 20.2) TO DARDANELLES (KM 26.6)

Durban 3 November 2023 – The construction of the northbound carriageway of the N3 has been proceeding well and the northbound traffic can now be diverted onto the newly constructed carriageway between Cato Ridge Interchange and Camperdown Interchange, the South African National Roads Agency SOC Limited (SANRAL) has announced.

“The switchover shall be done at night commencing from 5pm on Thursday, 9 November 2023 until 5am on Friday, 10 November 2023. The southbound traffic shall continue using the lanes currently used. The target date for switching the southbound traffic to contraflow between Camperdown Interchange and Cato Ridge Interchange is 11 December 2023. Contraflow conditions between Camperdown Interchange and Dardanelles will not be affected by this traffic switch and shall remain in contraflow,” said Thabiso Dladla, SANRAL’s Eastern Region Project Manager.

Once the traffic has been diverted off the southbound carriageway between Camperdown and Cato Ridge Interchanges, the existing southbound carriageway will be available for the total reconstruction of the new four lane southbound carriageway. It is expected that contraflow conditions shall prevail until January 2025.

The speed limit along the route has been reduced to 80km/hr to improve safety to the construction team and road users. Lane closures to permit construction vehicles safely entering and exiting the work zone can be expected at night and the public will be informed in advance of such activity.

Delays are expected, as a result of the reduced speed limit and motorists are urged to plan their trips carefully and be vigilant along the road during their travels.

“SANRAL apologises to the motoring public for any inconvenience caused during the switchover. We appeal to road users to adhere to the road signs and speed limit when approaching and travelling through the construction site,” said Dladla.

SANRAL starts public consultation on proposed Interim Preferential Procurement Policy (PPP)

MEDIA RELEASE
SANRAL starts public consultation on proposed Interim Preferential Procurement Policy (PPP)

Cape Town, 31 October 2023 – The South African National Roads Agency SOC Limited (SANRAL) today hosted the first of a series of engagements at various venues throughout the country to consult stakeholders on a proposed Interim Preferential Procurement Policy (PPP).

The first of the stakeholder engagement sessions took place at SANRAL’s Western Region office in Belville, Cape Town, with more than 100 people in attendance. Stakeholders also gathered at satellite venues in Pacaltsdorp, George, in the Southern Cape and Kimberley in the Northern Cape, both of which were linked virtually to the Belville office. SANRAL’s Western Region covers both the Western Cape and Northern Cape.

SANRAL CEO Reginald Demana, Regional Manager Randall Cable and other senior SANRAL representatives engaged with interested and affected stakeholders on the proposed Interim Preferential Procurement Policy (PPP) and related matters. Issues raised by stakeholders also included opportunities for small, medium and large contractors, transformation of the construction industry, skills development and training, as well as SMME funding, amongst others.

Mr Demana likened tensions around the transformation of the construction industry with the transformation of rugby in the earlier years of democracy when the Springboks were criticised for being too white. Many years later, the entire nation was celebrating the fact that the Springboks have won their fourth Rugby World Cup, with Siya Kolisi as captain for the second time.

“There was a time when some people stood up and said ‘If we don’t introduce quotas in sport, we are not going to achieve transformation’. That was not so long ago – and some people were up in arms – but we went through that pain and together today we celebrate Siya Kolisi, we talk about him as a great captain, some would say the most successful, having lifted two World Cups. But there was a time at which he was probably seen as not good enough to make that team. There was a time when, for him to make it to that team, there had to be a target set for a certain number of players of colour.” The battle for diversity in the Springboks was a long-term vision which is similar to the transformation of the South African economy, said Mr Demana. SANRAL would continue to work towards transformation of the construction industry, he said.

The proposed Interim Preferential Procurement Policy (PPP) is open for comment for three (3) weeks until 17 November 2023. The document can be found on SANRAL’s website (www.nra.co.za) and various social media platforms. Embedded within the policy document is an email address (commentsppp@nra.co.za) to enable stakeholders to submit their comments.

N2 section 2 officially open at Botrivier

MEDIA RELEASE
N2 section 2 officially open at Botrivier

Western Cape, 30 October 2023 – The South African National Roads Agency SOC Limited (SANRAL) is happy to report that the N2 section 2 at Botrivier is now open to traffic. This follows a four week road closure, where a portion of the road washed away when the Bot River burst its banks during the recent heavy rains experienced in the Western Cape.

Emergency repairs were instituted as soon as the contractor could access the damaged section of the road and the team has been working under extended hours until at least 22h00 every night, as well as on weekends.

The reconstruction and repair of the road involved 3100m³ of rockfill, 112 tons of asphalt and hundreds of man hours spent on site.

“SANRAL is mindful of the strategic and economic importance of the N2 and appreciates the sacrifices made by road users in taking alternative routes, some in excess of 100km. To this extent we were committed to opening the road as soon as safely possible, as improved mobility and the resumption of economic activity are prioritised,” said SANRAL CEO, Reginald Demana.

Repair works were carried out with the utmost respect for the natural environment and the sensitive ecosystems within which the road exists. While every effort was made to speed up the work, careful consideration was given to environmental compliance.

“it is a huge relief to have the road open and for people, goods and services to once again have uninterrupted access to the N2. We want to thank road users for their patience during this time. Our gratitude also extends to the workers who, without hesitation, put shoulder to the wheel to get the road open in record time. Because of their dedication, we have managed to open the road sooner than anticipated”, said Randall Cable, SANRAL’s Western Region Manager.

Road users are reminded to drive with caution as clean-up operations and repair teams continue on various roads across the Province following the devasting floods of late September.

SANRAL PUBLISHES PROPOSED INTERIM PREFERENTIAL PROCUREMENT POLICY (PPP) AND BEGINS CONSULTATIONS WITH STAKEHOLDERS

MEDIA RELEASE
SANRAL PUBLISHES PROPOSED INTERIM PREFERENTIAL PROCUREMENT POLICY (PPP) AND BEGINS CONSULTATIONS WITH STAKEHOLDERS

Pretoria, 30 October 2023 – The South African National Roads Agency SOC Limited (SANRAL) has issued a proposed Interim Preferential Procurement Policy (PPP) which is open for comment for a period of three (3) weeks from today, 30 October 2023, until 17 November 2023. The document can be found on SANRAL’s website (www.nra.co.za) and various social media platforms. Embedded within the policy document is an email address (commentsppp@nra.co.za) to enable stakeholders to submit their comments.

SANRAL will also on Tuesday, 31 October 2023, start conducting a series of engagements at various venues throughout the country to consult stakeholders on the proposed PPP. The first of the stakeholder engagement sessions will take place at SANRAL’s Western Region office in Belville, Cape Town, and will also be linked virtually to venues in Pacaltsdorp, George, in the Southern Cape and also in Kimberley in the Northern Cape. SANRAL’s Western Region spans the provinces of Western Cape and Northern Cape.

In addition, SANRAL will conduct stakeholder engagement sessions, at which senior SANRAL managers will be present, in all other provinces as part of a PPP Roadshow over the next few weeks. Stakeholders should be on the lookout for dates and venues of the sessions in their regions/provinces. These will also be published on SANRAL’s online platforms.

The decision to withdraw SANRAL’s new Preferential Procurement Policy which came into effect in May 2023 was taken by the Board last Monday, 23 October 2023, after careful consideration of the legal challenges to the policy launched by construction companies in various courts across the country.

These legal challenges would have prevented SANRAL from processing tenders worth billions of Rands, with significant negative consequences for the economy, as well as thousands of construction-related jobs.

The main purpose of the stakeholder engagement meetings is to enable SANRAL to receive inputs and contributions from interested and affected stakeholders on the proposed Interim PPP.

SANRAL urges all relevant stakeholders to participate in this consultative process to facilitate a speedy resolution to any potential obstacles that would delay the roads agency from meeting its mandate to build and maintain the country’s road infrastructure network and pursue its transformation objectives.