TRAFFIC ADVISORY
SANRAL N2/N3 EB Cloete upgrades and road closures
Durban, 8 August 2024 – The placing of concrete beams for the new Wandsbeck Bridge over the N2 will result in road closures, the South African National Roads Agency SOC Limited (SANRAL) has announced.
“These closures are to enable safe working area for the cranes and other machinery required for the placing of concrete beams for the new Wandsbeck Bridge over the N2. This forms part of SANRAL’s major upgrade of the N2 North and South bound, and the EB Cloete Interchange,” said Jason Lowe, SANRAL’s Eastern Region Project Manager.
The dates for the closures are:
- N2, North Bound Road Fully Closed: 20:00, Sat 10 August 2024 to 04:00 Sunday 11 August 2024.
- N2, South Bound Road Fully Closed: 20:00, Sun 11 August 2024 to 04:00 Mon 12 August 2024.
As required for the safety of both road users and the construction team, full traffic accommodation plans are in place.
Trucks and heavy vehicles are advised to try and delay trips over this period and/or find suitable staging areas to avoid major congestion. Public transport operators are asked to ensure their drivers are aware of route closures and alternatives affecting their commuter routings.
Light vehicle traffic, as well as emergency services and traffic management, are advised to make use of alternative routing.
A detailed alternative routing guide is included below and can be found on this link: www.nra.co.za
All road-users are advised to plan their routes ahead of time and where possible leave for destinations earlier than usual.
N2, NORTH BOUND ROAD FULLY CLOSED: 20:00, SATURDAY 10 AUGUST 2024 TO 04:00 SUNDAY 11 AUGUST 2024.
N2 and N3 ramps closed as follows at EB Cloete Interchange (AKA Spaghetti Junction) N3/N2 Interchange:
N2 North Bound (Amanzimtoti to Umhlanga):
- N2 fully closed North bound at EB Cloete interchange – can only proceed to N3 East bound (towards Durban) or West bound (towards Pinetown)
N3 West bound (Durban to Pinetown):
- Ramp closed to N2 North (to Umhlanga/King Shaka International Airport) – can only proceed to N2 South or N3 towards Pinetown
N3 East bound (Pinetown to Durban):
- Ramp closed to N2 North (to Umhlanga/King Shaka International Airport) – can only proceed to N2 South or N3 towards Durban
N2, SOUTH BOUND LANE CLOSURES: 20:00, SUNDAY 11 AUGUST 2024 TO 04:00 MONDAY 12 AUGUST 2024.
N2 and M19 ramps closed as follows:
N2/Umgeni Road (M19) Interchange
- M19: No access to N2 South (towards Durban)
Inanda Road Interchange
- N2 South Bound: No access to N2 South
“SANRAL appeals to road users to note and comply with the advance warning signs and speed restrictions when travelling towards and through the construction work zones. To prioritise the safety of both the construction workers and road users, the speed limit along the route will be reduced during construction,” said Lowe.
//Ends