TRAFFIC ADVISORY
N2 EB Cloete upgrades and road closures
Durban, 15 November 2024 – The South African National Roads Agency SOC Limited (SANRAL) has announced temporary road closures on the N2, allowing for the removal of bridge beams used in the King Cetshwayo (M13) Bridge construction over the N2.
Closure of the N2 southbound and N2 northbound carriageways between the EB Cloete Interchange (Spaghetti Junction) and the Umgeni Road Interchange will be as follows:
- Closure 1: N2 South Bound Closure – Saturday, 23 November 2024, at 20:00 to Sunday, 24 November 2024, at 04:00.
- Closure 2: N2 North Bound Closure – Sunday, 24 November 2024, at 20:00 to Monday, 25 November 2024, at 04:00.
- Closure 3: N2 South Bound Closure – Saturday, 30 November 2024, at 20:00 to Sunday, 1 December 2024, at 04:00.
- Closure 4: N2 North Bound Closure – Sunday, 1 December 2024, at 20:00 to Monday, 2 December 2024, at 04:00.
“This work is part of SANRAL’s major national road network upgrade to relieve traffic congestion across the province, enhancing the N2 North and South Bound and the EB Cloete Interchange,” said Jason Lowe, SANRAL’s Project Manager in the Eastern Region.
To ensure safety for both road users and the construction team, full traffic accommodation plans are in place, with signage, barriers and traffic-calming measures already installed.
“Trucks and heavy vehicles are advised to delay trips over these times or use staging areas to minimise congestion. Public transport operators should ensure drivers are aware of route closures and alternative routes affecting their schedules. Light vehicles and emergency services are encouraged to use alternative routes,” said Lowe.
A detailed alternative route guide is included below and can be found on this link: https://www.nra.co.za/project-n2n3-upgrades?region_id=eastern
All road users are strongly advised to plan routes in advance and leave for destinations earlier than usual to avoid delays.
More details about closures
Closure 1: N2 South Bound Closure – Saturday, 23 November 2024, at 20:00 to Sunday, 24 November 2024, at 04:00.
Closure 3: N2 South Bound Closure – Saturday, 30 November 2024, at 20:00 to Sunday, 1 December 2024, at 04:00.
N2 closed as follows:
- Umgeni Road (M19)/N2 Interchange: No access to N2 South (towards Amanzimtoti). N2 North (to Umhlanga/King Shaka International Airport) and M19 fully open.
- Inanda Road Interchange: No access to N2 South (to Amanzimtoti). N2 North (towards Umhlanga/King Shaka International Airport) and Inanda Road fully open.
Closure 2: N2 Noth Bound Closure – Sunday, 24 November 2024, at 20:00 to Monday, 25 November 2024, at 04:00.
Closure 4: N2 North Bound Closure – Sunday, 1 December 2024, at 20:00 to Monday, 2 December 2024, at 04:00.
N2 closed as follows:
- N3 West Bound (Durban to Pinetown): Ramp to N2 North (to Umhlanga/King Shaka International Airport) closed.
- N3 East Bound (Pinetown to Durban): Ramp to N2 North (to Umhlanga/King Shaka International Airport) closed.
- N2 North Bound at EB Cloete Interchange (aka Spaghetti Junction): N2 North closed between EB Cloete and Umgeni Interchanges. Access only to N3 East or West bound at EB Cloete.
“SANRAL appeals to road users to note and comply with the advance warning signs and speed restrictions when travelling past the construction work zones. To prioritise the safety of both the construction workers and road users, the speed limit along the route will be reduced during construction,” said Lowe.