Durban, 21 October 2026 – The South African National Roads Agency SOC Limited (SANRAL) advises motorists of temporary closures of the N2 off-ramps at the EB Cloete Interchange.

“Closures of the N2 off-ramps to the N3 are required to allow intricate works to take place on the bridge supports,” said Jason Lowe, SANRAL’s KwaZulu-Natal Provincial Office Road Safety Specialist Engineer.

The temporary road closure will take place as follows:

  • N2 North bound offramp to N3 East bound (from Amanzimtoti to Durban CBD):
  • This ramp will be fully closed from:
  • 18:00, Saturday 31 October 2026 to 18:00, Sunday 01 November 2026
  • 18:00, Saturday 14 November 2026, to 18:00 on Sunday, 15 November 2026
  • Note: the off-ramp to N3 West bound (from Amanzimtoti to Pietermaritzburg) remains open.
  • N2 South bound offramp to N3 westbound (from Umhlanga to Pietermaritzburg):
  • This ramp will be fully closed from:
  • 18:00, Saturday 07 November 2026 to 18:00, Sunday 08 November 2026
  • 18:00, Saturday 21 November 2026 to 18:00, on Sunday 22 November 2026
  • Note: the off-ramp to N3 East bound (from Umhlanga to Durban CBD) remains open.

As required for the safety of both road users and the construction team, full traffic accommodation plans and detour signage will be in place.

Trucks and heavy vehicles are advised to try and delay trips over this period, find suitable staging areas or reroute using the alternative route options to avoid major congestion. Public transport operators are asked to ensure their drivers are aware of route closures and alternatives affecting their commuter routes.

All road-users are advised to plan their routes ahead of time and where possible leave for destinations earlier than usual.

A detailed alternative route guide can be found at this link: https://www.nra.co.za/project-n2n3-upgrades?region_id=eastern

CLOSURE LOCATIONS:

N2 North bound offramp to N3 East bound (from Amanzimtoti to Durban CBD) at N2/N3 EB Cloete Interchange (aka Spaghetti Junction):

  • Full offramp closure
  • The remainder of the interchange, including the N2 North bound offramp towards Pietermaritzburg remains fully open to traffic

N2 South bound offramp to N3 West bound (from Umhlanga to Pietermaritzburg) at N2/N3 EB Cloete Interchange (aka Spaghetti Junction):

  • Full offramp closure
  • The remainder of the interchange, including the N2 South bound offramp towards Durban CBD remains fully open to traffic

“SANRAL fully appreciates the disruption that road closures can cause. To reduce the impact the time periods for these closures have been minimised, and they have been planned to take place over weekends to minimise weekday traffic disruption. The remainder of the EB Cloete Interchange remains fully open to traffic,” added Lowe.

__________________________________________________________________________________

For editorial content or additional information contact Lwando Mahlasela on 082 440 5305 pressoffice@nra.co.za